Monday, March 6, 2017

Week of 3/6/17

West Project:
Mainline pipe installation will continue starting at the intersection of S Novato Blvd and Redwood and then head east on S Novato Blvd. Work on the S Novato Blvd bike path will also continue. There will be a smaller crew installing services along Redwood Blvd and also potholing in various locations throughout the project.

East Project:
Mainline installation will continue along Vintage Way. Some hard rock was encountered last week which slowed progress, but we are hopeful to get out of it soon. There will also be a small crew installing steel brackets on the bridge going over Novato creek. You may also see a small potholing operation in various parts of the alignment.