Monday, July 31, 2017

Week of 7/31/17

West Project:
The HDD operation to Norman Tank has been finished and crews will be doing final clean up and site restoration.

East Project:
Paving is finished and crews will be working on restoration and clean up throughout the project.

Monday, July 17, 2017

Week of 7/17/17

West Project:
The horizontal drilling operation has slipped a few days. Work will continue into next week.

East Project:
The paving operation is continuing into the Vintage Oaks area. We expect it to be finished by the end of this week. Striping will then take place next week. Punch list items and clean up would then follow.

Tuesday, July 11, 2017

Week of 7/10/17

West Project:
The boring operation is nearly complete. We are hoping to have the hole completed and the pipe pulled in by the end of this week. Next week there will be some work on Entrada Dr to tie in the pipe that was pulled into the bored hole and the pipe recently installed in the street. If all goes well this could be done by the end of next week.

East Project:
Pavement restoration is underway. The crew is working from the North end of Rowland Way and headed south. This work will continue in to next week as well. There will also be small crews working on cleanup and restoration throughout the project.