Friday, April 28, 2017

Week of 4/30/17

West Project:
The last of the mainline installation is scheduled to take place on the bike path/fire road connecting Redwood Blvd. Concrete repairs will be taking place on S Novato Blvd and Rowland Blvd. Pavement restoration will also start on Wednesday. The operation will start on Redwood Blvd and head onto S Novato Blvd, then jump to Entrada Dr and then Ignacio Blvd.

East Project:
Service installations will continue throughout the alignment. Some steel pipe installation will take place on Vintage Way. There will also be work starting in Slade Park near the railroad tracks.

Friday, April 21, 2017

Bus Stop On Rowland Blvd Just East of S Novato Blvd - Closed 4/24/17

The bus stop on Rowland Blvd just East of S Novato Blvd will be closed on 4/24/17. The following notice will be posted there.

USE BUS STOP AT INTERSECTION OF SOUTH NOVATO BLVD & ROWLAND BLVD FOR SOUTHERLY LOCATIONS

USE BUS STOP AT INTERSECTION OF ROWLAND BLVD AND REDWOOD BLVD FOR VINTAGE OAKS AREA

Week of 4/23/17

East Project:
Mainline pipe installation will continue on Louis Dr. and is expected to take 3-5 days to complete.
A second crew will be installing services throughout the alignment.

West Project:
Mainline pipe installation will take place towards the middle to end of the week. A second crew will be installing services on S Novato Blvd and Redwood Blvd. There will also be concrete repairs made on Entrada Dr and Ignacio Blvd.

Friday, April 7, 2017

Week of 4/10/17

West Project:
Mainline installation will continue on Ignacio to start the week. Crews will then shift to S Novato Blvd near Lynwood school and continue mainline installation headed north and then onto Rowland Blvd. A small crew will remain on Ignacio to install the services.

East Project:
Pipeline installation will continue near Sutter Hospital headed towards Slade Park. Potholing will also take place at the Novato Sanitary Plant.