Friday, April 21, 2017

Bus Stop On Rowland Blvd Just East of S Novato Blvd - Closed 4/24/17

The bus stop on Rowland Blvd just East of S Novato Blvd will be closed on 4/24/17. The following notice will be posted there.

USE BUS STOP AT INTERSECTION OF SOUTH NOVATO BLVD & ROWLAND BLVD FOR SOUTHERLY LOCATIONS

USE BUS STOP AT INTERSECTION OF ROWLAND BLVD AND REDWOOD BLVD FOR VINTAGE OAKS AREA

Week of 4/23/17

East Project:
Mainline pipe installation will continue on Louis Dr. and is expected to take 3-5 days to complete.
A second crew will be installing services throughout the alignment.

West Project:
Mainline pipe installation will take place towards the middle to end of the week. A second crew will be installing services on S Novato Blvd and Redwood Blvd. There will also be concrete repairs made on Entrada Dr and Ignacio Blvd.

Friday, April 7, 2017

Week of 4/10/17

West Project:
Mainline installation will continue on Ignacio to start the week. Crews will then shift to S Novato Blvd near Lynwood school and continue mainline installation headed north and then onto Rowland Blvd. A small crew will remain on Ignacio to install the services.

East Project:
Pipeline installation will continue near Sutter Hospital headed towards Slade Park. Potholing will also take place at the Novato Sanitary Plant.