East Project

PROJECT 2

Location: This portion of the work is generally bounded by Davidson St. on the North, Vintage Way (Costco) on the South, the Novato Sanitary District Treatment Plant on Rowland Blvd. on the East, and Highway 101 on the West.

Construction Duration: January 2017 – September 2017

Typical Working Hours:  8:00 AM to 5:00 PM, Mon.-Fri.

Project Highlights: Includes construction of 1.9 miles of recycled water pipeline including approximately 7,300 feet of 16-inch PVC pipe, 2,300 feet of 12-inch PVC pipe, and approximately 750 feet of 16-inch welded steel pipe across the Novato Creek Bridge.