Wednesday, December 6, 2017

November-December Update

Highway 101 Crossing
There is some jute netting for erosion control placed on both the East Highway 101 and West Highway 101 construction sites, where the receiving and jacking pits have been backfilled and all work is complete.  All construction equipment has been demobilized.  The contractor has finished all project work as of November 30th, and the project will be officially closed out in December 2017 by the North Marin Water District. 



Norman Tank
The contractor has ensured that work shall only take place during working hours, which are 8:00 AM to 5:00 PM, Mon.-Fri. and if special approved is granted, 10:00AM-5:00PM on Saturday. No Saturday work is anticipated for the remainder of the project.  The vault excavation is complete, and the vault along with all necessary piping will be placed on 12/9/17.  This is the bulk of the work left for the project, leaving only site grading and miscellaneous items to be performed. The contractor will be finishing up all project work by the end of December 2017, after which the project will be officially closed by the North Marin Water District in January of 2017.

A few hours will be spent at Plum St tank (at the end of Zandra Pl).  This involves swapping out a valve for a motorized valve and this work is scheduled for mid December.  After this is complete, no more work will be performed on Zandra Pl. for this project.
 

Thursday, September 28, 2017

Activities for the End of September to Early October

Highway 101 Crossing 

The contractor is working on both the east and west of Highway 101. He will get the steel casing installed beneath the highway using a jack and bore trenchless method that utilizes a pilot tube for guidance. Once the protective casing is installed the recycled water main will be pushed into place and then tested.

No changes foreseen to their traffic control or staging areas at this time. The Project is scheduled to be complete in November of 2017. 

Remeber to slow for the cone zone!

Workers boring the pilot tube under Highway 101





















Norman Tank Project

The structural improvements are nearing completion and the Contractor has moved into the protective coatings phase. This will involve removing the existing coating with blast media, then priming and painting.

You will notice some noise during their work, and we appreciate your patience while they work as quickly as possible to finish!

Current completion of the project is the end of December 2017. 

Friday, August 18, 2017

Week of 8/18/17


Highway 101 Project 4 (Phase D)

Traffic control measures will be put into place next week on Redwood Blvd. and Vintage Oaks. It is intended to close one lane for the safety of the traveling public and the construction workers. 

For Redwood Blvd., there will be one lane closure in the Northbound direction but no expected road closure. For Vintage Oaks, there will be one lane closure in the Southbound direction near In-n-Out but no expected road closure.

Thanks for your patience and please remember to slow for the cone zone.

Monday, July 31, 2017

Week of 7/31/17

West Project:
The HDD operation to Norman Tank has been finished and crews will be doing final clean up and site restoration.

East Project:
Paving is finished and crews will be working on restoration and clean up throughout the project.

Monday, July 17, 2017

Week of 7/17/17

West Project:
The horizontal drilling operation has slipped a few days. Work will continue into next week.

East Project:
The paving operation is continuing into the Vintage Oaks area. We expect it to be finished by the end of this week. Striping will then take place next week. Punch list items and clean up would then follow.

Tuesday, July 11, 2017

Week of 7/10/17

West Project:
The boring operation is nearly complete. We are hoping to have the hole completed and the pipe pulled in by the end of this week. Next week there will be some work on Entrada Dr to tie in the pipe that was pulled into the bored hole and the pipe recently installed in the street. If all goes well this could be done by the end of next week.

East Project:
Pavement restoration is underway. The crew is working from the North end of Rowland Way and headed south. This work will continue in to next week as well. There will also be small crews working on cleanup and restoration throughout the project.