Friday, March 17, 2017

Week of 3/20/17

West Project:
Weather permitting, mainline installation will continue on Entrada for another 2-3 working days, then continue to Ignacio Blvd. towards the Country Club.  A second crew that is installing the recycled water lateral and meter will be through following the mainline for another 2-3 days total, although it may be intermittent work. This will be a small crew, about 5 workers. A third crew will be repairing sidewalk, curb, and gutter on Redwood Blvd as well.           

East Project:
Also weather permitting, mainline installation will continue on Vintage Way to Rowland Blvd, and then to Rowland Way. This will all be conducted at night. Working hours are 10:00PM-8:00AM. We ask you to please be extra cautious while driving through the area. The flaggers will do their best to get you through and if you have any questions or need help, please don't hesitate to ask one of them. A second crew will also be working at Slade Park excavating a pit for the bore and jack operation that will install pipe underneath the SMART Railroad tracks. This work will be performed during normal daytime working hours.

***Edit 3/20/17: Working hours are 10:00PM-8:00AM for the East side night work.