Tuesday, July 11, 2017

Week of 7/10/17

West Project:
The boring operation is nearly complete. We are hoping to have the hole completed and the pipe pulled in by the end of this week. Next week there will be some work on Entrada Dr to tie in the pipe that was pulled into the bored hole and the pipe recently installed in the street. If all goes well this could be done by the end of next week.

East Project:
Pavement restoration is underway. The crew is working from the North end of Rowland Way and headed south. This work will continue in to next week as well. There will also be small crews working on cleanup and restoration throughout the project.