Monday, June 26, 2017

Week of 6/26/17

West Project:
Work is continuing on the Norman Tank directional drill operation. The work in that area should be completed late next week or early the week of 7/9/17 if everything continues to go smoothly.

East Project:
Work at the NSD plant is in the final stages. The pipe that has been installed on Vintage Way, Rowland Blvd, and Rowland Way is also being pressure tested. Pavement restoration for the entire alignment will start next week, likely after the 4th of July holiday.