Friday, May 5, 2017

Week of 5/7/17

West Project:
Trench paving will continue on Entrada Dr and Igancio Blvd. The operation will then jump ahead to S Novato Blvd and Rowland Blvd and should be completed by the end of the week. Once paving is complete, a small crew will work on placing the lids to the utility boxes in the new pavement. A second crew will be working on the Redwood Blvd Bike Path finishing the last of the mainline pipe installation.

East Project:
There will be multiple operations going on throughout the week. There will be a crew backfilling the pits on either side of the railroad tracks near Slade Park. A second crew will be installing services throughout the alignment. A third crew will install pipe on Rowland Way. There will likely be a fourth crew installing steel pipe on the Novato Creek Bridge.