Thursday, May 18, 2017

Week of 5/21/17

West Project:
Street striping and traffic marking replacement will take place throughout the entire alignment. There will also be landscape work in the medians on Ignacio Blvd, S Novato Blvd and/or Redwood Blvd.

A Horizontal Directional Drill (HDD) operation will start mobilizing to Entrada Blvd sometime in June. Additional details will be posted here as we get closer to the start of work.

East Project:
Services will be installed throughout the alignment. Work will also take place at the Novato Sanitary Plant. A third crew may be on Rowland Way finishing installation of a storm drain crossing.