Friday, April 28, 2017

Week of 4/30/17

West Project:
The last of the mainline installation is scheduled to take place on the bike path/fire road connecting Redwood Blvd. Concrete repairs will be taking place on S Novato Blvd and Rowland Blvd. Pavement restoration will also start on Wednesday. The operation will start on Redwood Blvd and head onto S Novato Blvd, then jump to Entrada Dr and then Ignacio Blvd.

East Project:
Service installations will continue throughout the alignment. Some steel pipe installation will take place on Vintage Way. There will also be work starting in Slade Park near the railroad tracks.