Friday, April 21, 2017

Week of 4/23/17

East Project:
Mainline pipe installation will continue on Louis Dr. and is expected to take 3-5 days to complete.
A second crew will be installing services throughout the alignment.

West Project:
Mainline pipe installation will take place towards the middle to end of the week. A second crew will be installing services on S Novato Blvd and Redwood Blvd. There will also be concrete repairs made on Entrada Dr and Ignacio Blvd.