Friday, February 17, 2017

Week of 2/20/2017

West Project:
Mainline installation will start on the South side of the bike path on Redwood Blvd. Based on the current forecast, this probably won't start until mid-late week though. A smaller crew will be working on Redwood Blvd on the North side of the bike path installing services and appurtenances.

East Project:
Potholing operations will continue near Vintage Oaks and Rowland Way. We are hopeful that mainline installation will also start near Costco and head North on Vintage Way. This is also weather dependent, but looks likely for mid-late week.