Thursday, February 2, 2017

2/2/17 and Week of 2/6/17

Work on the west contract has been slowed due to rain. Once there is a break in the weather, they will get back to mainline pipe installation on Redwood. Pipe will be installed to the base of the bike path that connects Redwood. For the couple of days that work is taking place in that area you should expect minor delays, but the path will remain open. Once the pipe is installed at the base of the path, we will jump ahead to the other side of the path and continue installation in the roadway along Redwood Blvd.

On the east side, there will be a small crew potholing near Vintage Oaks. Potholing will continue into next week as well. If the rain lets up, mainline installation should start later next week near Costco.