Friday, December 30, 2016

Week of 1/2/2017

Work will be back underway on the west side after a week off. Crews will be installing mainline pipe and services on Redwood Blvd starting near Margarita Terrace and heading south.
In the next couple weeks, work on the East side will get started as well. The work will start with installation of project signs and implementation of the SWPPP (stormwater pollution prevention program). Pipe installation is planned to start near Slade park and work north toward Novato Sanitary District's treatment plant. We will be sure to post more details as they become more clear. Have a happy New Years everybody!