The NMWD Central Expansion Project Blog is intended as a community outreach tool, to keep the public informed with construction activities, status and information.
Friday, February 24, 2017
Bike Path Closure
Thankfully the weather has given us the break we needed to start the bike path work. Our plan is to close the path at 7:00AM Monday, 2/27 at which time shuttle service will start. The locations for shuttle pickup and dropoff will be a section of the parking area on S Novato Blvd and the far east end of Entrada; see Google maps attached. The shuttle schedule will run from 7:00AM to 11:00PM Monday, 2/27 and then from 5:00AM to 11:00PM daily for the two week closure period which is scheduled to end on 3/12. After the full closure period, the shuttle will run weekdays from 7:30AM to 5:00PM for approximately 2 additional weeks for the path work to be completed. During this time the path will be open after hours and on weekends.