PROJECT 4
Location: This portion of the work will be accessed from Redwood Rd. on the West and Vintage Parkway on the East.
Construction Duration: January 2017 – August 2017
Typical
Working Hours: 8:00 AM to 5:00 PM,
Mon.-Fri.
Project
Highlights: Involves a trenchless pipe installation under Highway 101 to
connect the West Project 1 with the East Project 2.