West Project:
The last of the mainline installation is scheduled to take place on the bike path/fire road connecting Redwood Blvd. Concrete repairs will be taking place on S Novato Blvd and Rowland Blvd. Pavement restoration will also start on Wednesday. The operation will start on Redwood Blvd and head onto S Novato Blvd, then jump to Entrada Dr and then Ignacio Blvd.
East Project:
Service installations will continue throughout the alignment. Some steel pipe installation will take place on Vintage Way. There will also be work starting in Slade Park near the railroad tracks.
The NMWD Central Expansion Project Blog is intended as a community outreach tool, to keep the public informed with construction activities, status and information.
Friday, April 28, 2017
Friday, April 21, 2017
Bus Stop On Rowland Blvd Just East of S Novato Blvd - Closed 4/24/17
The bus stop on Rowland Blvd just East of S Novato Blvd will be closed on 4/24/17. The following notice will be posted there.
USE BUS STOP AT INTERSECTION OF SOUTH NOVATO BLVD & ROWLAND BLVD FOR SOUTHERLY LOCATIONS
USE BUS STOP AT INTERSECTION OF ROWLAND BLVD AND REDWOOD BLVD FOR VINTAGE OAKS AREA
USE BUS STOP AT INTERSECTION OF SOUTH NOVATO BLVD & ROWLAND BLVD FOR SOUTHERLY LOCATIONS
USE BUS STOP AT INTERSECTION OF ROWLAND BLVD AND REDWOOD BLVD FOR VINTAGE OAKS AREA
Week of 4/23/17
East Project:
Mainline pipe installation will continue on Louis Dr. and is expected to take 3-5 days to complete.
A second crew will be installing services throughout the alignment.
West Project:
Mainline pipe installation will take place towards the middle to end of the week. A second crew will be installing services on S Novato Blvd and Redwood Blvd. There will also be concrete repairs made on Entrada Dr and Ignacio Blvd.
Mainline pipe installation will continue on Louis Dr. and is expected to take 3-5 days to complete.
A second crew will be installing services throughout the alignment.
West Project:
Mainline pipe installation will take place towards the middle to end of the week. A second crew will be installing services on S Novato Blvd and Redwood Blvd. There will also be concrete repairs made on Entrada Dr and Ignacio Blvd.
Friday, April 7, 2017
Week of 4/10/17
West Project:
Mainline installation will continue on Ignacio to start the week. Crews will then shift to S Novato Blvd near Lynwood school and continue mainline installation headed north and then onto Rowland Blvd. A small crew will remain on Ignacio to install the services.
East Project:
Pipeline installation will continue near Sutter Hospital headed towards Slade Park. Potholing will also take place at the Novato Sanitary Plant.
Mainline installation will continue on Ignacio to start the week. Crews will then shift to S Novato Blvd near Lynwood school and continue mainline installation headed north and then onto Rowland Blvd. A small crew will remain on Ignacio to install the services.
East Project:
Pipeline installation will continue near Sutter Hospital headed towards Slade Park. Potholing will also take place at the Novato Sanitary Plant.
Friday, March 24, 2017
Week of 3/27/17
West Project:
Mainline installation will continue starting on Entrada Blvd then heading West on Ignacio Blvd. Traffic control on Ignacio Blvd will include a closure of the Eastbound lanes. Flaggers will be present to direct traffic into the appropriate lanes at the nearest intersection.
Paving operations will continue on Redwood Blvd on Monday 3/27/17.
There may also be some light work done on the S Novato bike path.
East Project:
This week's night work on Vintage Way was slowed due to weather. The forecast is looking much better for next week though. We expect this work to continue from Vintage Way on Rowland Blvd and then to Rowland Way. Working hours will be 10 PM - 8 AM.
Mainline installation will continue starting on Entrada Blvd then heading West on Ignacio Blvd. Traffic control on Ignacio Blvd will include a closure of the Eastbound lanes. Flaggers will be present to direct traffic into the appropriate lanes at the nearest intersection.
Paving operations will continue on Redwood Blvd on Monday 3/27/17.
There may also be some light work done on the S Novato bike path.
East Project:
This week's night work on Vintage Way was slowed due to weather. The forecast is looking much better for next week though. We expect this work to continue from Vintage Way on Rowland Blvd and then to Rowland Way. Working hours will be 10 PM - 8 AM.
Mainline installation on Davidson Street is expected to
begin on Monday 3/27/17. Construction will begin near the intersection of Louis
Drive and Davidson Street as shown with the yellow highlighted area on the map below.
One way traffic control will be setup around the work area with hold times of
up to 4 minutes. Construction activities along Davidson Street are expected to
last three to five days. Construction start time is 8:00am.
Due to encountering an unexpected utility on Louis Drive,
construction activities are expected to be limited for several days next week.
No Parking signs will be adjusted to provide residents with additional parking
during the reduced construction activities.
Tuesday, March 21, 2017
Paving Rowland and Redwood Blvd
Starting on Thursday 3/23 a paving crew will be performing the final paving over the trench sections on Rowland and Redwood Blvd. Below is a map to provide more details. The yellow line represents the area that will be paved this week. The blue-green line represents the area that pipe has been installed and is being tested. This section will be paved in the future once it has passed a hydrostatic test. If the weather cooperates, the paving crew should be done with this section by Friday 3/24.
Friday, March 17, 2017
Bike Path Update
Good news! The bike path will reopen for use on Saturday 3/18/17. Weather permitting, some work will still take place during normal work hours next week. While work is ongoing the shuttle service will be provided. If work is not taking place, the path will be open to use. Thank you for your patience.