Friday, December 30, 2016

Week of 1/2/2017

Work will be back underway on the west side after a week off. Crews will be installing mainline pipe and services on Redwood Blvd starting near Margarita Terrace and heading south.
In the next couple weeks, work on the East side will get started as well. The work will start with installation of project signs and implementation of the SWPPP (stormwater pollution prevention program). Pipe installation is planned to start near Slade park and work north toward Novato Sanitary District's treatment plant. We will be sure to post more details as they become more clear. Have a happy New Years everybody!

Tuesday, December 20, 2016

Week of 12/19/2016

The rain slowed us down last week, but we are back to work this week. There will be a large crew working on pipeline installation on Redwood Ave starting near Scottsdale Way and heading south. Another small crew will be installing appurtenances such as hydrants and air valves on Redwood Blvd where the mainline pipe has already been installed. The HDD crew near Entrada Dr is cleaning up for the next few days as well.  There is no work scheduled to take place next week.

Friday, December 2, 2016

Week of 12/5/2016

Pipeline installation will be continuing on Redwood Blvd for the week of 12/5/16. Crews will be starting near Scottsdale Pond and heading south. Redwood Blvd will be open to vehicular traffic. Traffic will move in both directions in the East lane. Cones, signs, and other traffic control measures will be in place to direct traffic flow.